RVRailVision AI
RailVision AI · Control room · JK Cement Jaisalmer

Railway Siding — Lanela Station → JKCL Yard

CH 0+428 to CH 23+754 · Status sheets as of 10 Oct 2026

Overall progress
14.1%
weighted estimate
42.4%
Cutting 1,38,125 / 3,26,000 cum
14.1%
Filling 53,185 / 3,78,500 cum
12.2%
Blanketing 7,034 / 57,600 cum
0.0%
Track linking 0 / 28,082 m

Strip chart by chainage

Under progressCompletedNot started
Cutting / Filling
22% done · 72% active
Blanketing 1st layer
7% done · 10% active
Blanketing 2nd layer
2% done · 6% active
Track linking
0% done · 0% active
1234567891011121314151617181920212223RUB-01BC-02BC-03BC-04RUB-05BC-06RUB-07RUB-08BC-09RUB-10*BC-11*BC-12*BC-13*RUB-13RUB-14
km · red line = SRC | Sumcon

Tap anywhere on the chart or a structure to see site photos at that chainage

M/s SRC Company Infra Pvt. Ltd

CH 0+428 → CH 15+500 · Target Feb 2027

Track work

Excavation / Cutting (Outside Plant)18.3%
40,445 / 2,21,000 Cum · bal 1,80,555Oct: 11,551 / 68,000 (17%)

In progress CH 5+000–6+000 & CH 9+000–9+500

Filling (Outside Plant)5.1%
13,087 / 2,55,000 Cum · bal 2,41,913Oct: 4,761 / 50,000 (10%)

Excavated soil used in filling CH 8+000–9+000; outside soil STP not received

Blanketing0.0%
0 / 33,500 Cum · bal 33,500Oct: 0 / 5,000 (0%)

Blanketing material not finalised

Track Linking0.0%
0 / 15,072 Mtr · bal 15,072

Structures (RUB 4 + 1 Nos, Box 8 Nos)

Excavation2.1%
330 / 15,475 Cum · bal 15,145Oct: 110 / 300 (37%)

RUB 1 & 5, Box 3 & 4 excavation complete

PCC1.8%
14 / 800 Cum · bal 786Oct: 14 / 60 (23%)

RUB 1 & 5, Box 3 PCC complete

RCC0.4%
22 / 5,800 Cum · bal 5,778Oct: 22 / 350 (6%)

RUB 5 & Box 3 raft casting complete

M/s Sumcon Infraventures

CH 15+500 → CH 23+754 · Target Dec 2026

Track work

Excavation (Inside Plant)100.0%
73,000 / 73,000 Cum · bal 0

Completed

Excavation / Cutting (Outside Plant)77.1%
24,680 / 32,000 Cum · bal 7,320Oct: 1,104 / 8,424 (13%)

In progress CH 15+500–16+000

Filling (Outside Plant)32.5%
40,098 / 1,23,500 Cum · bal 83,402Oct: 7,080 / 50,000 (14%)

In progress CH 19+500–20+000

Blanketing29.2%
7,034 / 24,100 Cum · bal 17,066Oct: 2,510 / 14,000 (18%)

Final layer complete CH 21+700–22+100

Track Linking0.0%
0 / 13,010 Mtr · bal 13,010Oct: 0 / 3,600 (0%)

Starts 16 Oct 2026

Structures (RUB 2 Nos)

Excavation13.6%
1,534 / 11,275 Cum · bal 9,741Oct: 50 / 1,200 (4%)
PCC5.0%
25 / 500 Cum · bal 475Oct: 0 / 40 (0%)
RCC3.5%
122 / 3,500 Cum · bal 3,378Oct: 22 / 180 (12%)

RUB 14 wall 1st lift casting complete

Structures — RUBs & Box Culverts

Combined: 5.5% (2,047 / 37,350 cum)

M/s SRC Company Infra Pvt. Ltd

RUB 4 + 1 Nos, Box 8 Nos
Excavation2.1%
330 / 15,475 Cum · bal 15,145Oct: 110 / 300
RUB 1 & 5, Box 3 & 4 excavation complete
PCC1.8%
14 / 800 Cum · bal 786Oct: 14 / 60
RUB 1 & 5, Box 3 PCC complete
RCC0.4%
22 / 5,800 Cum · bal 5,778Oct: 22 / 350
RUB 5 & Box 3 raft casting complete

M/s Sumcon Infraventures

RUB 2 Nos
Excavation13.6%
1,534 / 11,275 Cum · bal 9,741Oct: 50 / 1,200
PCC5.0%
25 / 500 Cum · bal 475Oct: 0 / 40
RCC3.5%
122 / 3,500 Cum · bal 3,378Oct: 22 / 180
RUB 14 wall 1st lift casting complete

Structure locations are marked on the strip chart above (RUB-01 … RUB-14, BC-02 … BC-13). Figures = status sheets + approved daily structure entries. * = chainage estimated (CH 10–15 km drawing not yet provided); target = SRC overall, 28 Feb 2027.

Completion forecast

Estimated from this month's daily rate (status sheets + site entries over 10 days since 1 Oct 2026) and compared with each contractor's target.

M/s SRC Company Infra Pvt. Ltd · Target 28 Feb 2027

ActivityRate/dayNeeded/dayForecastStatus
Excavation / Cutting (Outside Plant)1,155 Cum1,281 Cum16 Mar 20271 mo late
Filling (Outside Plant)476 Cum1,716 Cum2 Mar 202812 mo late
Blanketing0238 CumCannot forecastNo progress
Track Linking0107 MtrCannot forecastNo progress
Structures – Excavation11 Cum108 Cum18 Jul 203041 mo late
Structures – PCC1 Cum6 Cum24 Apr 202814 mo late
Structures – RCC2 Cum41 Cum19 Dec 203383 mo late

M/s Sumcon Infraventures · Target 31 Dec 2026

ActivityRate/dayNeeded/dayForecastStatus
Excavation (Inside Plant)——CompletedDone
Excavation / Cutting (Outside Plant)110 Cum90 Cum16 Dec 2026On track
Filling (Outside Plant)708 Cum1,018 Cum5 Feb 20271 mo late
Blanketing251 Cum209 Cum17 Dec 2026On track
Track Linking0159 MtrCannot forecastNo progress
Structures – Excavation5 Cum119 Cum10 Feb 203262 mo late
Structures – PCC06 CumCannot forecastNo progress
Structures – RCC2 Cum42 Cum24 Dec 203048 mo late

Structure-wise forecast (RUB / Box culvert)

From approved daily site entries for each structure. Each structure's quantity is estimated as an equal share of its contractor's total, because the status sheets don't split it by structure.

M/s SRC Company Infra Pvt. Ltd · Target 28 Feb 2027

StructureExcavationPCCRCCForecast finish
RUB-01 · 1.259✅✅—No site rate yet
BC-02 · 2.035———No site rate yet
BC-03 · 2.383✅✅—No site rate yet
BC-04 · 2.535✅——No site rate yet
RUB-05 · 3.385✅✅—No site rate yet
BC-06 · 4.000———No site rate yet
RUB-07 · 8.736———No site rate yet
RUB-08 · 8.900———No site rate yet
BC-09 · 9.716———No site rate yet
RUB-10 · 11.000———No site rate yet
BC-11 · 12.250———No site rate yet
BC-12 · 13.500———No site rate yet
BC-13 · 14.750———No site rate yet

M/s Sumcon Infraventures · Target 31 Dec 2026

StructureExcavationPCCRCCForecast finish
RUB-13 · 17.125———No site rate yet
RUB-14 · 22.158———No site rate yet

Rate = quantity entered for that structure ÷ days since its first entry (from 1 Oct 2026 onward).

Overall % is a weighted estimate — use "Adjust weights" above to change them; your choice is saved on this device. Strip chart positions are read from the drawings; CH 10–15 km drawing not provided, shown as not started.