M/s SRC Company Infra Pvt. Ltd
CH 0+428 → CH 15+500 · Target Feb 2027
Track work
In progress CH 5+000–6+000 & CH 9+000–9+500
Excavated soil used in filling CH 8+000–9+000; outside soil STP not received
Blanketing material not finalised
Structures (RUB 4 + 1 Nos, Box 8 Nos)
RUB 1 & 5, Box 3 & 4 excavation complete
RUB 1 & 5, Box 3 PCC complete
RUB 5 & Box 3 raft casting complete