Status sheet figures plus approved site entries. "Oct plan" is the monthly plan from the sheets.

M/s SRC Company Infra Pvt. Ltd

CH 0+428 → CH 15+500 · target 28 Feb 2027

0
Site entries
0
Pending approval
0
Overlap flags
ActivityDone / ScopeLeft%Oct plan vs actual
Excavation / Cutting (Outside Plant)40,445 / 2,21,000 Cum1,80,55518.311,551 / 68,000 (17%)
Filling (Outside Plant)13,087 / 2,55,000 Cum2,41,9135.14,761 / 50,000 (10%)
Blanketing0 / 33,500 Cum33,5000.00 / 5,000 (0%)
Track Linking0 / 15,072 Mtr15,0720.0—
Structures · Excavation330 / 15,475 Cum15,1452.1110 / 300 (37%)
Structures · PCC14 / 800 Cum7861.814 / 60 (23%)
Structures · RCC22 / 5,800 Cum5,7780.422 / 350 (6%)
Last approved site entry: none yet

M/s Sumcon Infraventures

CH 15+500 → CH 23+754 · target 31 Dec 2026

0
Site entries
0
Pending approval
0
Overlap flags
ActivityDone / ScopeLeft%Oct plan vs actual
Excavation (Inside Plant)73,000 / 73,000 Cum0100.0—
Excavation / Cutting (Outside Plant)24,680 / 32,000 Cum7,32077.11,104 / 8,424 (13%)
Filling (Outside Plant)40,098 / 1,23,500 Cum83,40232.57,080 / 50,000 (14%)
Blanketing7,034 / 24,100 Cum17,06629.22,510 / 14,000 (18%)
Track Linking0 / 13,010 Mtr13,0100.00 / 3,600 (0%)
Structures · Excavation1,534 / 11,275 Cum9,74113.650 / 1,200 (4%)
Structures · PCC25 / 500 Cum4755.00 / 40 (0%)
Structures · RCC122 / 3,500 Cum3,3783.522 / 180 (12%)
Last approved site entry: none yet